          SITEREPORT
        
        
          Olympic vision
        
        
          Also on this part of the site is an 800-room hotel for the press,
        
        
          a ‘VIP’ hotel, numerous outdoor sports facilities, car parks,
        
        
          restaurants and cafes.
        
        
          All the buildings on the Olympic Complex are in the striking
        
        
          architectural style that canbe seen throughout Ashgabat. Shortly
        
        
          after gaining independence from theUSSR in1991, a distinctive
        
        
          stylewas developed for the city, which sees newbuildings clad in
        
        
          white marble with dark-tinted windows – often in dark blue to
        
        
          contrast with themarble. Gold is used to highlight architectural
        
        
          features and for lettering onbuildings.
        
        
          By and large, the buildings are of a steel frame construction
        
        
          design, but they are also complex because they need to meet a
        
        
          variety of requirements anddesign specifications.
        
        
          “We held a lot of meetings with international federations and
        
        
          local representatives because Olympic facilities need to meet
        
        
          certain standards, but they also need to meet the needs of local
        
        
          athletes,” saidMrKarakus.
        
        
          He added, “Another challenge is that we are building somany
        
        
          different types of building – arenas, indoor venues, hotels, the
        
        
          VIPhotel, themonorail, theOlympicVillage, and so on.
        
        
          “Wehit a lot of existing services on this site, plus all theutilities
        
        
          on this project are inter-linked - so you can’t just pick one
        
        
          structure and go andbuild it.”
        
        
          Andwithin each venue there are different challenges.The sheer
        
        
          size of the buildings and their roof spans are perhaps the most
        
        
          difficult. For example, the Velodrome has a 130m span end-to-
        
        
          end, which involvedplacing a 350 tonne steel roof truss.
        
        
          “Planning that lift alone was a real challenge in terms of
        
        
          ensuring health& safety, themethod statement and so on,” said
        
        
          MrKarakus.
        
        
          Under construction
        
        
          When
        
        
          
            iC
          
        
        
          visited the Olympic site in February, construction
        
        
          work on Phase II of the project to the North of the site was in
        
        
          full swing, with Phase III – the central portion containing the
        
        
          45,000 seater outdoor arena and Olympic Village underway,
        
        
          but at an earlier stage.The Olympic Village will comprise some
        
        
          57,000m
        
        
          2
        
        
          of accommodation across 14 tower blocks.
        
        
          The three main venues in Phase II are the 5,000 seater indoor
        
        
          athletics arena, the aquatics centre, which also seats 5,000 and
        
        
          features both indoor and outdoor 50 m racing pools as well as
        
        
          deepdiving pools, and the 4,000 capacity indoor tennis arena.
        
        
          In addition to the venues, spread across the three phases of
        
        
          The 5,000-seater
        
        
          indoor athletics
        
        
          arena at the
        
        
          Northern end of
        
        
          the site.
        
        
          The view down
        
        
          the 50m indoor
        
        
          pool, with the
        
        
          diving pool
        
        
          beyond. There is
        
        
          also an outside
        
        
          50m pool and
        
        
          diving pool.
        
        
          Inside the 15,000 seater indoor arena,
        
        
          whichwill be used for basketball,
        
        
          gymnastics, badminton and table
        
        
          tennis, among other sports.
        
        
          Finish quality
        
        
          inside the
        
        
          venues is high
        
        
          and includes
        
        
          upholstered
        
        
          leather seats for
        
        
          spectators.